Dynamics of construction in May

31/05/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in May.

House 1
Section 1

Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 95%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%

Section 2
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%

Section 3
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 76%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 75%.
Installation of elevators and commissioning - 6%


Section 4
Roof installation - 90%.
Installation of facades - 75%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%
Finishing of common areas and special rooms - 71%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 66%.

Section 5
Installation of a monolith of the 23th floor
Masonry walls 18 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 3%.

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 14 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 5%

House 2
Section 8
Arrangement monolithic frame below zero - 80%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%

Section 9
Arrangement monolithic frame below zero - 80%

Section 10
Arrangement pits - 80%
Foundation plate device - 60%


See the full photo report in the section "Construction progress"

Related news

Watch all
11/03/2022
Важлива інформація про оплату на виплат
Увага! Важлива інформація. Наразі з технічних причин компанія «Інтергал-Буд» не приймає оплати за об’єкти неру...
05/02/2024
«Укргазбанк» акредитував ЖК "Причал 8" до участі в єОселя
Державний «Укргазбанк» акредитував об'єкти на етапі будівництва від компанії «Інтергал-Буд» до участі у пільго...
02/02/2021
Dynamics of construction in January
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
02/11/2021
Dynamics of construction in October 2021
Dear customers! For your attention the dynamics of construction of the residential complex "Prychal-8" for Oct...
13/04/2021
«Інтергал-Буд» презентував іміджеві відео про квартири з ремонтами та меблями
Цієї весни будівельна компанія «Інтергал-Буд» запропонувала споживачам нову опцію — повністю мебльовані кварти...
23/12/2024
Графік роботи відділів продажу на різдвяно-новорічні свята
Шановні клієнти, Раді повідомити графік роботи наших відділів продажу під час свят: 25 та 31 грудня, 1 та ...
29/11/2024
Будинок 2 ЖК «Причал 8» введено в експлуатацію!
Маємо чудову новину для майбутніх мешканців ЖК «Причал 8» – будинок 2 офіційно введено в експлуатацію! А отже,...
20/02/2020
Intergal-Bud at its own expense installed lighting on Kanalnaya street
Creating modern complexes in which it is comfortable to live, raise children, work and develop is the purpose ...
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...