Dynamics of construction in May

31/05/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in May.

House 1
Section 1

Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 95%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%

Section 2
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%

Section 3
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 76%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 75%.
Installation of elevators and commissioning - 6%


Section 4
Roof installation - 90%.
Installation of facades - 75%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%
Finishing of common areas and special rooms - 71%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 66%.

Section 5
Installation of a monolith of the 23th floor
Masonry walls 18 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 3%.

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 14 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 5%

House 2
Section 8
Arrangement monolithic frame below zero - 80%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%

Section 9
Arrangement monolithic frame below zero - 80%

Section 10
Arrangement pits - 80%
Foundation plate device - 60%


See the full photo report in the section "Construction progress"

Related news

Watch all
03/08/2022
Динаміка будівництва станом на 1 серпня 2022 року
Наразі тривають роботи в будинку №1.  В секціях №1 та №2 ведуться роботи зі встановлення пожежної сигналізаці...
02/11/2021
Working hours of the sales department during the period of epidemiological restrictions
Dear customer! Please note that during the period of tightening the restrictions to prevent the spread of COV...
04/11/2020
Residential complex PRYCHAL 8 presented to buyers a showroom of apartments with designer renovations
On November 1, on the territory of the residential complex PRYCHAL 8 (Kyiv, Kanalnaya st., 8), a showroom of a...
25/07/2024
Будинки від «Інтергал-Буд» матимуть автономне електроживлення
З огляду на складну ситуацію в українській енергетиці компанія «Інтергал-Буд» прийняла рішення внести корек...
18/11/2021
Дохід від інвестицій до 10% у валюті – портал «Мінфін»
Журналісти ресурсу «Мінфін» встановили, скільки зможуть заробити інвестори, придбавши квартиру у Києві для под...
05/02/2024
«Укргазбанк» акредитував ЖК "Причал 8" до участі в єОселя
Державний «Укргазбанк» акредитував об'єкти на етапі будівництва від компанії «Інтергал-Буд» до участі у пільго...
18/12/2023
ГРАФІК РОБОТИ ВІДДІЛІВ ПРОДАЖІВ «ІНТЕРГАЛ-БУД» НА СВЯТА
Шановні клієнти, зверніть, будь ласка, увагу, що відділи продажів компанії «Інтергал-Буд» на період зимових св...
25/12/2022
Акційний курс при достроковому погашенні розтермінування
Компанія «Інтергал-Буд» йде на зустріч своїм клієнтам та пропонує вигідні умови дострокового погашення заборго...
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...