Dynamics of construction in May

31/05/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in May.

House 1
Section 1

Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 95%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%

Section 2
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%

Section 3
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 76%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 75%.
Installation of elevators and commissioning - 6%


Section 4
Roof installation - 90%.
Installation of facades - 75%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%
Finishing of common areas and special rooms - 71%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 66%.

Section 5
Installation of a monolith of the 23th floor
Masonry walls 18 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 3%.

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 14 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 5%

House 2
Section 8
Arrangement monolithic frame below zero - 80%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%

Section 9
Arrangement monolithic frame below zero - 80%

Section 10
Arrangement pits - 80%
Foundation plate device - 60%


See the full photo report in the section "Construction progress"

Related news

Watch all
02/02/2021
Dynamics of construction in January
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
22/12/2020
Графік роботи відділів продажів компанії «Інтергал-Буд» на новорічні свята
Шановні покупці, вітаємо з прийдешнім Новим роком та Різдвом Христовим й повідомляємо про графік роботи наших ...
30/12/2021
Динамика строительства за декабрь 2021
Дом 1 В секции 1, 2, 3, 4 На 98% завершено устройство системы внутреннего водоснабжения и канализации, отопл...
02/05/2024
ГРАФІК РОБОТИ ВІДДІЛІВ ПРОДАЖІВ КОМПАНІЇ НА ВЕЛИКОДНІ СВЯТА
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи відділів пр...
31/03/2020
We invite you to a video excursion in the territory of Prychal-8
Head of Sales Tatiana Cherednyk will show and tell you everything you wanted to know about the complex with "l...
21/12/2022
Графік роботи на свята
Шановні клієнти, зверніть, будь ласка, увагу, що відділ продажів ЖК "Причал 8" та відділ супроводу договорів к...
04/11/2020
Residential complex PRYCHAL 8 presented to buyers a showroom of apartments with designer renovations
On November 1, on the territory of the residential complex PRYCHAL 8 (Kyiv, Kanalnaya st., 8), a showroom of a...
02/10/2019
On October 5, children are invited to the "Pier 8" residential complex for a "Happy Brick" excursion
We know what your kids have this Saturday! They are definitely interesting and will spend time on an interacti...
12/04/2024
Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики
Компанія «Інтергал-Буд» вносить зміни у всі договори купівлі-продажу нерухомості, додавши пункт про усуненн...