Dynamics of construction in May

31/05/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in May.

House 1
Section 1

Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 95%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%

Section 2
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%

Section 3
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 76%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 75%.
Installation of elevators and commissioning - 6%


Section 4
Roof installation - 90%.
Installation of facades - 75%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%
Finishing of common areas and special rooms - 71%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 66%.

Section 5
Installation of a monolith of the 23th floor
Masonry walls 18 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 3%.

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 14 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 5%

House 2
Section 8
Arrangement monolithic frame below zero - 80%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%

Section 9
Arrangement monolithic frame below zero - 80%

Section 10
Arrangement pits - 80%
Foundation plate device - 60%


See the full photo report in the section "Construction progress"

Related news

Watch all
11/12/2024
Динаміка будівництва на 11.12.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 11.12.2024 року. Будинок №2 зданий в експлуа...
03/03/2021
«Інтергал-Буд» першим серед девелоперів приєднався до державної програми «Доступна іпотека 7%»
З 1 березня в Україні стартувала державна програма «Доступна іпотека 7%». Компанія «Інтергал-Буд» стала першим...
13/07/2020
Globus Bank have improved the conditions for mortgage loans
We bring to your attention current mortgage program from Globus Bank. Find out about the conditions here: ht...
04/11/2020
Residential complex PRYCHAL 8 presented to buyers a showroom of apartments with designer renovations
On November 1, on the territory of the residential complex PRYCHAL 8 (Kyiv, Kanalnaya st., 8), a showroom of a...
31/03/2021
Dynamics of construction in March
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
25/11/2020
«Intergal-Bud» and «Ukrgasbank» have improved mortgage conditions
We are pleased to announce that «Intergal-Bud», in partnership with JSB «Ukrgasbank», has offered its clients ...
30/12/2021
Динамика строительства за декабрь 2021
Дом 1 В секции 1, 2, 3, 4 На 98% завершено устройство системы внутреннего водоснабжения и канализации, отопл...
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
23/12/2024
Графік роботи відділів продажу на різдвяно-новорічні свята
Шановні клієнти, Раді повідомити графік роботи наших відділів продажу під час свят: 25 та 31 грудня, 1 та ...