Dynamics of construction in May

31/05/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in May.

House 1
Section 1

Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 95%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%

Section 2
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%

Section 3
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 76%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 75%.
Installation of elevators and commissioning - 6%


Section 4
Roof installation - 90%.
Installation of facades - 75%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%
Finishing of common areas and special rooms - 71%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 66%.

Section 5
Installation of a monolith of the 23th floor
Masonry walls 18 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 3%.

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 14 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 5%

House 2
Section 8
Arrangement monolithic frame below zero - 80%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%

Section 9
Arrangement monolithic frame below zero - 80%

Section 10
Arrangement pits - 80%
Foundation plate device - 60%


See the full photo report in the section "Construction progress"

Related news

Watch all
29/08/2019
First time on the market! Apartments in "INTERGAL-BUD" with a choice of redecoration
INTERGAL-BUD is inclined to be a style and trend setter. A few years ago, the company was the first in the mar...
01/07/2021
Dynamics of construction in June
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
13/10/2021
Графік роботи відділу продажів у святкові дні жовтня 2021 року
Шановні клієнти, Звертаємо вашу увагу на зміни графіку роботи відділу продажів житлового комплексу «Причал8»....
12/04/2021
Візьміть участь у конкурсі «Сад на балконі» від «Інтергал-Буд»!
Закохані у ландшафтний дизайн та навіть брак території вас не зупинив, і ви змогли створити зелену оазу на вла...
14/06/2021
«Інтергал-Буд» оголошує старт першого футбольного турніру ІНТЕРГАЛ-БУД CUP серед житлових комплексів
Поки уся Європа в передчутті початку довгоочікуваного Євро-2020, будівельна компанія «Інтергал-Буд» оголошує с...
22/02/2024
БУДИНОК №1 ОТРИМАВ ПОШТОВУ АДРЕСУ
Маємо чудові новини, будинок №1 житлового комплексу «Причал 8» отримав адресу: вулиця Канальна, 8. Вже незаба...
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
02/11/2020
Dynamics of construction in October
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
11/12/2023
Динаміка будівництва станом на 11.12.2023 року.
Шановні інвестори! До вашої уваги динаміка будівництва станом на 11.12.2023 року. Будинок №2     Секція 8 ...