Dynamics of construction in October 2021

02/11/2021

Dear customers! For your attention the dynamics of construction of the residential complex "Prychal-8" for October 2021:

House 1

Sections 1, 2, 3, 4

The installation of the internal water supply and sewerage system, heating, power supply, and fire-fighting systems has been completed by 97%.

Section 3

Elevator installation and commissioning is 95% complete. The finishing of common areas and special premises is 97% complete. The installation of metal-plastic structures, entrance doors to apartments and doors are nearing completion.

Section 4

The work on the installation of metal-plastic structures, the entrance door to apartments and common areas are approaching the completion. The installation of elevators and commissioning works, which have already been completed by 90%, continue.

Section 5

Work on the construction of facades continues (80%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work continues on the installation of internal water supply and sewerage systems, heating, power supply and fire protection systems. Finishing works for common areas and special premises are 60% completed. Installation of elevators and commissioning are 60% completed.

Section 6, 7

The construction of the monolith and brickwork was completed. The work on the installation of elevators is in progress, finishing work and work on the laying of internal engineering networks have begun.

 

House 2

Section 8

The waterproofing and insulation of the basement of the building has been completed by 95%. The construction of a monolithic frame on the 14th floor continues. Work is underway to install metal structures to reinforce brickwork on floors 2-9.

Section 9

The setup of waterproofing, insulation of the basement of the building is being completed. The construction of a monolithic frame continues. Work continues on the installation of ventilation blocks and flights of stairs up to the 12th floor.

Section 10

Work is underway to install metal structures to reinforce brickwork on floors 2-9. Work continues on the installation of ventilation blocks and flights of stairs up to the 12th floor. Also, on the 14th floor, work continues on the construction of vertical elements of the building's monolithic frame.

The setup of external networks of the complex is in progress.

 

Related news

Watch all
18/12/2019
Prychal 8. Construction of 1 and 2 sections of the house №1 is completed
Twenty floors in less than a year. "Intergal-Bud" has completed construction of 1.2 sections of the seven-sect...
01/09/2020
Dynamics of construction in August
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
02/03/2026
Житловий комплекс «Причал 8» обладнаний власною даховою котельнею
Комфорт мешканців залишається ключовим пріоритетом у будь-яку пору року. Саме тому житловий комплекс «Причал 8...
02/10/2019
On October 5, children are invited to the "Pier 8" residential complex for a "Happy Brick" excursion
We know what your kids have this Saturday! They are definitely interesting and will spend time on an interacti...
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...
13/07/2020
Globus Bank have improved the conditions for mortgage loans
We bring to your attention current mortgage program from Globus Bank. Find out about the conditions here: ht...
21/12/2022
Графік роботи на свята
Шановні клієнти, зверніть, будь ласка, увагу, що відділ продажів ЖК "Причал 8" та відділ супроводу договорів к...
25/11/2020
«Intergal-Bud» and «Ukrgasbank» have improved mortgage conditions
We are pleased to announce that «Intergal-Bud», in partnership with JSB «Ukrgasbank», has offered its clients ...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...