Dynamics of construction in October 2021

02/11/2021

Dear customers! For your attention the dynamics of construction of the residential complex "Prychal-8" for October 2021:

House 1

Sections 1, 2, 3, 4

The installation of the internal water supply and sewerage system, heating, power supply, and fire-fighting systems has been completed by 97%.

Section 3

Elevator installation and commissioning is 95% complete. The finishing of common areas and special premises is 97% complete. The installation of metal-plastic structures, entrance doors to apartments and doors are nearing completion.

Section 4

The work on the installation of metal-plastic structures, the entrance door to apartments and common areas are approaching the completion. The installation of elevators and commissioning works, which have already been completed by 90%, continue.

Section 5

Work on the construction of facades continues (80%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work continues on the installation of internal water supply and sewerage systems, heating, power supply and fire protection systems. Finishing works for common areas and special premises are 60% completed. Installation of elevators and commissioning are 60% completed.

Section 6, 7

The construction of the monolith and brickwork was completed. The work on the installation of elevators is in progress, finishing work and work on the laying of internal engineering networks have begun.

 

House 2

Section 8

The waterproofing and insulation of the basement of the building has been completed by 95%. The construction of a monolithic frame on the 14th floor continues. Work is underway to install metal structures to reinforce brickwork on floors 2-9.

Section 9

The setup of waterproofing, insulation of the basement of the building is being completed. The construction of a monolithic frame continues. Work continues on the installation of ventilation blocks and flights of stairs up to the 12th floor.

Section 10

Work is underway to install metal structures to reinforce brickwork on floors 2-9. Work continues on the installation of ventilation blocks and flights of stairs up to the 12th floor. Also, on the 14th floor, work continues on the construction of vertical elements of the building's monolithic frame.

The setup of external networks of the complex is in progress.

 

Related news

Watch all
05/03/2021
Working hours of sales department for March 8
We draw your attention to the fact that our sales department on March 8 will work on a weekend schedule - from...
18/12/2023
ГРАФІК РОБОТИ ВІДДІЛІВ ПРОДАЖІВ «ІНТЕРГАЛ-БУД» НА СВЯТА
Шановні клієнти, зверніть, будь ласка, увагу, що відділи продажів компанії «Інтергал-Буд» на період зимових св...
25/12/2022
Акційний курс при достроковому погашенні розтермінування
Компанія «Інтергал-Буд» йде на зустріч своїм клієнтам та пропонує вигідні умови дострокового погашення заборго...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
24/07/2024
ОБМЕЖЕННЯ ЕЛЕКТРОПОСТАЧАННЯ НЕ ВПЛИВАЄ НА ТЕМПИ БУДІВНИЦТВА ПРОЄКТІВ «ІНТЕРГАЛ-БУД»
З метою забезпечення безперервної роботи бригад на будмайданчиках компанія «Інтергал-Буд» закупила потужні ген...
17/08/2021
Майбутні мешканці ЖК «Причал 8» відсвяткували Медовий Спас
14 серпня на території житлового комплексу «Причал 8» святкували Медовий Спас. Девелопер «Інтергал-Буд» влашту...
13/04/2023
Графік роботи відділу продажів
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи в наступні ...
29/08/2019
First time on the market! Apartments in "INTERGAL-BUD" with a choice of redecoration
INTERGAL-BUD is inclined to be a style and trend setter. A few years ago, the company was the first in the mar...
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...