Dynamics of construction in June

01/07/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in June.

House 1
Section 1

Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 87%

Section 2
Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 96%

Section 3
Roof installation - 90%.
Installation of facades - 93%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Installation of elevators and commissioning - 10%


Section 4
Roof installation - 90%.
Installation of facades - 84%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 86%.
Installation of elevators and commissioning - 5%

Section 5
Installation of a roof
Masonry walls 19 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 20%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 2%

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 16 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 95%
Arrangement of a monolithic framework (2 part) - 85%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 6%

House 2
Section 8
Arrangement monolithic frame below zero - 100%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%
Monolithic frame device above zero - 5%

Section 9
Arrangement monolithic frame below zero - 100%
Monolithic frame device above zero - 4%

Section 10
Arrangement pits - 95%
Arrangement monolithic frame below zero - 95%
Monolithic frame device above zero - 6%


See the full photo report in the section "Construction progress"

Related news

Watch all
16/12/2021
Графік роботи відділу продажів у святкові дні
Шановні клієнти, Звертаємо вашу увагу на зміни графіку роботи відділу продажів у святкові дні. 25-27 грудня ...
13/07/2023
Відновлення будівництва будинку №2
Маємо чудові новини для інвесторів 2 будинку в ЖК «Причал 8». Компанія «Інтергал-Буд» відновила будівельні роб...
02/02/2021
Dynamics of construction in January
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
18/06/2021
Переїзд відділу продажів ЖК "Причал 8"
Шановні інвестори! З радістю повідомляємо, що відділ продажів переїхав у нове приміщення! Відтепер чекаємо ва...
31/03/2021
Dynamics of construction in March
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
27/04/2021
Графік роботи відділу продажів у святкові дні травня 2021 року
Шановні клієнти! Вітаємо з прийдешніми святами та звертаємо вашу увагу на зміни в графіку роботи відділу прод...
28/05/2020
Construction Dynamics for May 2020
Dear customers! Your apartments with incredible views of the left bank of the Dnieper do not stop being built!...
15/07/2024
«ІНТЕРГАЛ-БУД» ОБЛАШТУЄ УКРИТТЯ У КОЖНОМУ ЖИТЛОВОМУ БУДИНКУ
Компанія «Інтергал-Буд» реалізує плани щодо облаштування безпечних приміщень для мешканців своїх будинків, в я...
23/12/2024
Графік роботи відділів продажу на різдвяно-новорічні свята
Шановні клієнти, Раді повідомити графік роботи наших відділів продажу під час свят: 25 та 31 грудня, 1 та ...