Dynamics of construction in June

01/07/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in June.

House 1
Section 1

Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 87%

Section 2
Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 96%

Section 3
Roof installation - 90%.
Installation of facades - 93%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Installation of elevators and commissioning - 10%


Section 4
Roof installation - 90%.
Installation of facades - 84%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 86%.
Installation of elevators and commissioning - 5%

Section 5
Installation of a roof
Masonry walls 19 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 20%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 2%

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 16 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 95%
Arrangement of a monolithic framework (2 part) - 85%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 6%

House 2
Section 8
Arrangement monolithic frame below zero - 100%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%
Monolithic frame device above zero - 5%

Section 9
Arrangement monolithic frame below zero - 100%
Monolithic frame device above zero - 4%

Section 10
Arrangement pits - 95%
Arrangement monolithic frame below zero - 95%
Monolithic frame device above zero - 6%


See the full photo report in the section "Construction progress"

Related news

Watch all
31/05/2021
Dynamics of construction in May
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
13/04/2023
Графік роботи відділу продажів
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи в наступні ...
27/04/2021
Графік роботи відділу продажів у святкові дні травня 2021 року
Шановні клієнти! Вітаємо з прийдешніми святами та звертаємо вашу увагу на зміни в графіку роботи відділу прод...
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
15/12/2020
«Інтергал-Буд» дарує 1 квадратний метр усім охочим!
«Інтергал-Буд» вітає з прийдешніми новорічними святами та дарує усім тим, хто хоче придбати квартиру, 1 квадра...
18/11/2021
Дохід від інвестицій до 10% у валюті – портал «Мінфін»
Журналісти ресурсу «Мінфін» встановили, скільки зможуть заробити інвестори, придбавши квартиру у Києві для под...
05/03/2021
Working hours of sales department for March 8
We draw your attention to the fact that our sales department on March 8 will work on a weekend schedule - from...
24/07/2024
ОБМЕЖЕННЯ ЕЛЕКТРОПОСТАЧАННЯ НЕ ВПЛИВАЄ НА ТЕМПИ БУДІВНИЦТВА ПРОЄКТІВ «ІНТЕРГАЛ-БУД»
З метою забезпечення безперервної роботи бригад на будмайданчиках компанія «Інтергал-Буд» закупила потужні ген...