Dynamics of construction in June

01/07/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in June.

House 1
Section 1

Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 87%

Section 2
Installation of elevators and commissioning - 96%
Finishing of common areas and special rooms - 96%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 96%

Section 3
Roof installation - 90%.
Installation of facades - 93%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 85%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Installation of elevators and commissioning - 10%


Section 4
Roof installation - 90%.
Installation of facades - 84%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 82%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 86%.
Installation of elevators and commissioning - 5%

Section 5
Installation of a roof
Masonry walls 19 floors
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 20%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 2%

Section 6
Installation of a monolith of the 20nd floor
Masonry walls 16 floors

Section 7
Installation of a monolith of the 14nd floor
Masonry walls 10 floors

Parking
Arrangement of a monolithic framework (1 part) - 95%
Arrangement of a monolithic framework (2 part) - 85%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 6%

House 2
Section 8
Arrangement monolithic frame below zero - 100%
Arrangement of a waterproofing, warming of a cellar part of the building - 20%
Monolithic frame device above zero - 5%

Section 9
Arrangement monolithic frame below zero - 100%
Monolithic frame device above zero - 4%

Section 10
Arrangement pits - 95%
Arrangement monolithic frame below zero - 95%
Monolithic frame device above zero - 6%


See the full photo report in the section "Construction progress"

Related news

Watch all
17/03/2020
Intergal-Bud launches INTERGAL-Online, its own Telegram channel and virtual tours in showrooms
Real estate at any time, even in the most turbulent times, was and remains a reliable investment and a guarant...
03/08/2022
Динаміка будівництва станом на 1 серпня 2022 року
Наразі тривають роботи в будинку №1.  В секціях №1 та №2 ведуться роботи зі встановлення пожежної сигналізаці...
29/11/2023
«СКАЙ БАНК» акредитував об'єкти на первинці від «Інтергал-Буд» до участі в єОселя
Банк-партнер державної програми єОселя, «СКАЙ БАНК», акредитував об'єкти на етапі будівництва від компанії «Ін...
02/11/2021
Dynamics of construction in October 2021
Dear customers! For your attention the dynamics of construction of the residential complex "Prychal-8" for Oct...
14/10/2024
Динаміка будівництва на 02.10.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 02.10.2024 року. Будинок №2 Секція 8 Влашт...
13/06/2022
Відділ продажів ЖК «Причал 8» відновлює свою роботу
Чергова порція хороших новин від компанії «Інтергал-Буд». З 13 червня відділ продажів житлового комплексу ЖК «...
28/05/2020
Construction Dynamics for May 2020
Dear customers! Your apartments with incredible views of the left bank of the Dnieper do not stop being built!...
31/10/2022
ЖК «Причал 8» доєднується до програми «єОселя»
Компанія «Інтергал-Буд» вітає державну ініціативу, яка покликана зробити купівлю житлової нерухомості в іпотек...
20/08/2024
Зрілість та досвід: компанія «Інтергал-Буд» відзначає 21-річчя
Найбільший приватний забудовник України, компанія «Інтергал-Буд», святкує 21 рік з початку роботи на вітчизнян...