Dear customers! Your apartments with incredible views of the left bank of the Dnieper do not stop being built!
As of May 28, the dynamics of construction looks like this:
Section 1
Facade installation - 6%
Roof device - 85%
The device of walls and partitions - entrance groups - 99%
Installation of metal-plastic structures, entrance doors to apartments and doors of the MZK - 95%
Section 2
Monolithic frame device - 99%
Roof device - 78%
Installation of walls and partitions - 99%
Installation of metal-plastic structures, entrance doors to apartments and doors of the MZK - 75%
Section 3
Monolith device of the 20th floor
The device of walls and partitions of the 15th floor
Section 4
Horizontal element of the 18th floor
The device of walls and partitions of the 15th floor
Section 5
Foundation plate arrangement
Monolithic device 2 floors
For more photos, see the "Construction Progress" section.