Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
02/02/2021
Dynamics of construction in January
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
17/06/2021
Графік роботи відділу продажів у святкові дні червня 2021 року
Шановні клієнти! Звертаємо вашу увагу на графік роботи відділу продажів ЖК "Причал 8" у святкові дні: 21 чер...
11/03/2022
Важлива інформація про оплату на виплат
Увага! Важлива інформація. Наразі з технічних причин компанія «Інтергал-Буд» не приймає оплати за об’єкти неру...
09/10/2023
Динаміка будівництва станом на 09.10.2023 року.
Шановні інвестори! До вашої уваги динаміка будівництва станом на 09.10.2023 року. Будинок №2, секції №8-10  ...
17/08/2021
Майбутні мешканці ЖК «Причал 8» відсвяткували Медовий Спас
14 серпня на території житлового комплексу «Причал 8» святкували Медовий Спас. Девелопер «Інтергал-Буд» влашту...
16/12/2021
Графік роботи відділу продажів у святкові дні
Шановні клієнти, Звертаємо вашу увагу на зміни графіку роботи відділу продажів у святкові дні. 25-27 грудня ...
03/08/2022
Динаміка будівництва станом на 1 серпня 2022 року
Наразі тривають роботи в будинку №1.  В секціях №1 та №2 ведуться роботи зі встановлення пожежної сигналізаці...
01/07/2020
Dynamics of construction in June
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
11/09/2023
Динамика строительства по состоянию на 08.09.2023г.
Уважаемые инвесторы! Вашему вниманию динамика строительства по состоянию на 08.09.2023 года. Дом №2, секции №8...