Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
13/04/2023
Графік роботи відділу продажів
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи в наступні ...
09/03/2022
Зміни умов оплати за об’єкти нерухомості, придбані у тому числі у розстрочку
Шановні покупці, до вашої уваги важлива інформація! Компанія «Інтергал-Буд» продовжує приймати платежі за об’є...
31/05/2021
Dynamics of construction in May
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
23/12/2024
Графік роботи відділів продажу на різдвяно-новорічні свята
Шановні клієнти, Раді повідомити графік роботи наших відділів продажу під час свят: 25 та 31 грудня, 1 та ...
01/12/2020
Dynamics of construction in November
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
20/08/2024
Зрілість та досвід: компанія «Інтергал-Буд» відзначає 21-річчя
Найбільший приватний забудовник України, компанія «Інтергал-Буд», святкує 21 рік з початку роботи на вітчизнян...
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
01/07/2020
Dynamics of construction in June
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
20/10/2023
ОЩАДБАНК КРЕДИТУВАТИМЕ УКРАЇНЦІВ НА КУПІВЛЮ КВАРТИР ВІД «ІНТЕРГАЛ-БУД» ПІД 7%
Ощадбанк та найбільший приватний забудовник України «Інтергал-Буд» підписали меморандум про співпрацю, в рамка...