Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...
02/12/2021
Динамика строительства за ноябрь 2021
Уважаемые покупатели! Вашему вниманию динамика строительства ЖК "Причал-8" за ноябрь 2021: Дом 1 В секции 1,...
03/03/2021
Dynamics of construction in February
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
15/12/2020
«Інтергал-Буд» дарує 1 квадратний метр усім охочим!
«Інтергал-Буд» вітає з прийдешніми новорічними святами та дарує усім тим, хто хоче придбати квартиру, 1 квадра...
02/04/2021
«Інтергал-Буд» компенсуватиме клієнтам витрати на таксі
На період дії обмежень у роботі столичного громадського транспорту, з 5 квітня і по 16 квітня з можливим продо...
13/07/2020
Globus Bank have improved the conditions for mortgage loans
We bring to your attention current mortgage program from Globus Bank. Find out about the conditions here: ht...
13/04/2021
«Інтергал-Буд» презентував іміджеві відео про квартири з ремонтами та меблями
Цієї весни будівельна компанія «Інтергал-Буд» запропонувала споживачам нову опцію — повністю мебльовані кварти...
02/02/2021
Dynamics of construction in January
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
05/03/2021
Working hours of sales department for March 8
We draw your attention to the fact that our sales department on March 8 will work on a weekend schedule - from...

Want to get advice?

Contact sales managers and choose the best option