Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
13/06/2022
Відділ продажів ЖК «Причал 8» відновлює свою роботу
Чергова порція хороших новин від компанії «Інтергал-Буд». З 13 червня відділ продажів житлового комплексу ЖК «...
31/03/2020
We invite you to a video excursion in the territory of Prychal-8
Head of Sales Tatiana Cherednyk will show and tell you everything you wanted to know about the complex with "l...
17/08/2022
Інвестори ЖК «Причал 8» почали отримувати ключі від омріяних квартир
«Інтергал-Буд» невтомно працює, аби здійснювати мрії українців про власне нове житло. Так, нещодавно інвестори...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
18/05/2023
Інформація про виплати за програмами розтермінування
Увага! Важлива інформація для інвесторів проєктів «Інтергал-Буд», які придбали нерухомість на виплат та мають ...
20/10/2023
ОЩАДБАНК КРЕДИТУВАТИМЕ УКРАЇНЦІВ НА КУПІВЛЮ КВАРТИР ВІД «ІНТЕРГАЛ-БУД» ПІД 7%
Ощадбанк та найбільший приватний забудовник України «Інтергал-Буд» підписали меморандум про співпрацю, в рамка...
14/06/2021
«Інтергал-Буд» оголошує старт першого футбольного турніру ІНТЕРГАЛ-БУД CUP серед житлових комплексів
Поки уся Європа в передчутті початку довгоочікуваного Євро-2020, будівельна компанія «Інтергал-Буд» оголошує с...
01/09/2020
Dynamics of construction in August
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
10/05/2022
Контактні номери на період військового стану
«Інтергал-Буд» пишається українцями, бо в такий важкий час, ми всі тримаємося міцно.  Ми зібрали список важли...