Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
04/11/2020
Residential complex PRYCHAL 8 presented to buyers a showroom of apartments with designer renovations
On November 1, on the territory of the residential complex PRYCHAL 8 (Kyiv, Kanalnaya st., 8), a showroom of a...
14/06/2021
«Інтергал-Буд» оголошує старт першого футбольного турніру ІНТЕРГАЛ-БУД CUP серед житлових комплексів
Поки уся Європа в передчутті початку довгоочікуваного Євро-2020, будівельна компанія «Інтергал-Буд» оголошує с...
06/11/2023
Динамика строительства по состоянию на 06.11.2023 года.
Уважаемые инвесторы! Вашему вниманию динамика строительства по состоянию на 06.11.2023 года. Дом №2 Секция 8...
20/06/2024
ОЩАДБАНК АКРЕДИТУВАВ БУДИНОК №2 ЖК «ПРИЧАЛ 8» ДО УЧАСТІ В ЄОСЕЛЯ
Банк-партнер державної програми єОселя, Ощадбанк, розширив перелік об'єктів на етапі будівництва від компанії ...
11/12/2023
Динаміка будівництва станом на 11.12.2023 року.
Шановні інвестори! До вашої уваги динаміка будівництва станом на 11.12.2023 року. Будинок №2     Секція 8 ...
27/04/2021
Графік роботи відділу продажів у святкові дні травня 2021 року
Шановні клієнти! Вітаємо з прийдешніми святами та звертаємо вашу увагу на зміни в графіку роботи відділу прод...
14/10/2024
Динаміка будівництва на 02.10.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 02.10.2024 року. Будинок №2 Секція 8 Влашт...
21/12/2022
Графік роботи на свята
Шановні клієнти, зверніть, будь ласка, увагу, що відділ продажів ЖК "Причал 8" та відділ супроводу договорів к...