Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
25/11/2022
Єдина ціна + розтермінування
Мрієте жити біля озера і шукаєте однокімнатну квартиру для себе? Чи потрібна простора квартира для всієї родин...
25/11/2020
«Intergal-Bud» and «Ukrgasbank» have improved mortgage conditions
We are pleased to announce that «Intergal-Bud», in partnership with JSB «Ukrgasbank», has offered its clients ...
19/11/2022
Зміни у графіку роботи відділу продажів
Раді повідомити, що відтепер відділ продажів «Причал 8» працюватиме також і у вихідні дні. Чекаємо вас на конс...
03/08/2021
Dynamics of construction in July
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
22/12/2020
Графік роботи відділів продажів компанії «Інтергал-Буд» на новорічні свята
Шановні покупці, вітаємо з прийдешнім Новим роком та Різдвом Христовим й повідомляємо про графік роботи наших ...
13/07/2020
Globus Bank have improved the conditions for mortgage loans
We bring to your attention current mortgage program from Globus Bank. Find out about the conditions here: ht...
15/04/2025
Графік роботи відділів продажу на Великдень
Друзі, щиро вітаємо вас з прийдешнім Великоднем! 🐣 Бажаємо тепла, миру та радості у ваших домівках. Звертаєм...
18/12/2019
Prychal 8. Construction of 1 and 2 sections of the house №1 is completed
Twenty floors in less than a year. "Intergal-Bud" has completed construction of 1.2 sections of the seven-sect...
20/06/2024
ОЩАДБАНК АКРЕДИТУВАВ БУДИНОК №2 ЖК «ПРИЧАЛ 8» ДО УЧАСТІ В ЄОСЕЛЯ
Банк-партнер державної програми єОселя, Ощадбанк, розширив перелік об'єктів на етапі будівництва від компанії ...