Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!
House 1
In section №1, №2, №3, №4
Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.
Section 3
Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.
Finishing of common areas and special rooms is done by 96%
The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.
Section 4
They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.
Section 5
Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.
Section 6, 7
The installation of the monolith has been completed.
Parking
Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.
House 2
Section 8
Almost completed installation of waterproofing, insulation of the basement of the building.
Installation of a monolithic framework proceeds.
Section 9
The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.
Section 10
At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.