Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
20/08/2024
Зрілість та досвід: компанія «Інтергал-Буд» відзначає 21-річчя
Найбільший приватний забудовник України, компанія «Інтергал-Буд», святкує 21 рік з початку роботи на вітчизнян...
13/07/2020
Globus Bank have improved the conditions for mortgage loans
We bring to your attention current mortgage program from Globus Bank. Find out about the conditions here: ht...
12/04/2024
Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики
Компанія «Інтергал-Буд» вносить зміни у всі договори купівлі-продажу нерухомості, додавши пункт про усуненн...
15/12/2020
«Інтергал-Буд» дарує 1 квадратний метр усім охочим!
«Інтергал-Буд» вітає з прийдешніми новорічними святами та дарує усім тим, хто хоче придбати квартиру, 1 квадра...
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
28/04/2020
Dynamics of construction as of 23.04.20
Dear clients! We do not stop to create your dream apartments. We offer you to get acquainted with the up-to-da...
15/07/2024
«ІНТЕРГАЛ-БУД» ОБЛАШТУЄ УКРИТТЯ У КОЖНОМУ ЖИТЛОВОМУ БУДИНКУ
Компанія «Інтергал-Буд» реалізує плани щодо облаштування безпечних приміщень для мешканців своїх будинків, в я...
31/10/2022
ЖК «Причал 8» доєднується до програми «єОселя»
Компанія «Інтергал-Буд» вітає державну ініціативу, яка покликана зробити купівлю житлової нерухомості в іпотек...
12/04/2021
Візьміть участь у конкурсі «Сад на балконі» від «Інтергал-Буд»!
Закохані у ландшафтний дизайн та навіть брак території вас не зупинив, і ви змогли створити зелену оазу на вла...