Dynamics of construction in September

12/10/2021

Dear customers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

House 1

In section №1, №2, №3, №4

Installation of elevators and commissioning works and decoration of common areas have been completed. Also at the finish line installation of internal water supply and sewerage, heating, electricity, fire protection systems.

Section 3

Works on the arrangement of the roof, facades, internal water supply and sewerage system, heating, electricity supply, fire-fighting systems are almost completed.

Finishing of common areas and special rooms is done by 96%

The installation of metal-plastic structures, entrance doors to the apartment and MZK doors is being completed. Installation of elevators and commissioning work was performed by 92%.

Section 4

They are nearing completion of roofing, facades, internal water supply and sewerage systems, heating, electricity supply, fire-fighting systems, as well as work on the decoration of common areas. Installation of metal-plastic structures, entrance doors to apartments and public places is performed by more than 98%, and installation of elevators and commissioning - by 80%.

Section 5

Work on the installation of facades (70%). Installation of metal-plastic structures, entrance doors to apartments and common areas continues. Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire protection systems. Work on the decoration of common areas and special rooms is performed by 50%. Installation of elevators and commissioning work is performed by 50%.

Section 6, 7

The installation of the monolith has been completed.

Parking

Work is underway on the installation of internal water supply and sewerage systems, heating, electricity supply and fire safety.

House 2

Section 8

Almost completed installation of waterproofing, insulation of the basement of the building.

Installation of a monolithic framework proceeds.

Section 9

The installation of waterproofing, insulation of the basement of the building is being completed. Installation of a monolithic framework proceeds.

Section 10

At the finish line installation of waterproofing, insulation of the basement of the building. The device of a monolithic framework above zero is executed on 100%.

Related news

Watch all
15/07/2024
«ІНТЕРГАЛ-БУД» ОБЛАШТУЄ УКРИТТЯ У КОЖНОМУ ЖИТЛОВОМУ БУДИНКУ
Компанія «Інтергал-Буд» реалізує плани щодо облаштування безпечних приміщень для мешканців своїх будинків, в я...
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
07/06/2022
Центральний відділ продажів компанії «Інтергал-Буд» відновлює свою роботу
Раді повідомити, що центральний відділ продажів «Інтергал-Буд», який розташований у бізнес-центрі М8 за адресо...
02/02/2022
Динамика строительства за январь 2021
Уважаемые покупатели! Вашему вниманию динамика строительства ЖК "Причал-8" за январь 2022: Дом 1 В секции 1,...
31/03/2021
Dynamics of construction in March
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
02/04/2021
«Інтергал-Буд» компенсуватиме клієнтам витрати на таксі
На період дії обмежень у роботі столичного громадського транспорту, з 5 квітня і по 16 квітня з можливим продо...
29/11/2023
«СКАЙ БАНК» акредитував об'єкти на первинці від «Інтергал-Буд» до участі в єОселя
Банк-партнер державної програми єОселя, «СКАЙ БАНК», акредитував об'єкти на етапі будівництва від компанії «Ін...
02/10/2019
On October 5, children are invited to the "Pier 8" residential complex for a "Happy Brick" excursion
We know what your kids have this Saturday! They are definitely interesting and will spend time on an interacti...