Dynamics of construction in March

31/03/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in Мarch.

House 1
Section 1

Installation of facades - 97%
Roof installation - 100%.
Installation of elevators and commissioning - 90%
Finishing of common areas and special rooms - 85%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems -78%

Section 2
Roof installation - 99%.
Installation of facades - 98%
Installation of elevators and commissioning - 85%
Finishing of common areas and special rooms - 85%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 80%

Section 3
Roof installation - 60%.
Installation of facades - 60%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 70%
Finishing of common areas and special rooms - 55%

Section 4
Roof installation - 50%.
Installation of facades - 25%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 89%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 60%
Finishing of common areas and special rooms - 55%

Section 5
Installation of a monolith of the 16th floor
Masonry walls 11 floors

Section 6
Installation of a monolith of the 16nd floor
Masonry walls 9 floors

Section 7
Installation of a monolith of the 10nd floor
Masonry walls 8 floors

Parking
Arrangement of a monolithic framework (1 part) - 85%
Arrangement of a monolithic framework (2 part) - 85%

House 2
Section 8
Arrangement pits - 95%
Arrangement monolytnoho frame below zero - 10%

Section 9
Arrangement pits - 95%

Section 10
Arrangement pits - 80%


See the full photo report in the section "Construction progress"

Related news

Watch all
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
11/03/2022
Важлива інформація про оплату на виплат
Увага! Важлива інформація. Наразі з технічних причин компанія «Інтергал-Буд» не приймає оплати за об’єкти неру...
01/09/2022
Квартири з ремонтом від «Інтергал-Буд»
Інвестори 3 та 4 секцій будинку №1 ЖК «Причал 8» почали отримувати ключі від своїх квартир. І якщо для власник...
31/07/2020
Dynamics of construction as of 31.07.20
Dear buyers! We bring to your attention the monthly fixation of the dynamics of construction of the "Prychal 8...
29/11/2023
«СКАЙ БАНК» акредитував об'єкти на первинці від «Інтергал-Буд» до участі в єОселя
Банк-партнер державної програми єОселя, «СКАЙ БАНК», акредитував об'єкти на етапі будівництва від компанії «Ін...
14/08/2024
Динаміка будівництва на 14.08.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 14.08.2024 року. Будинок №2 Секція 8 Влашт...
15/12/2020
«Інтергал-Буд» дарує 1 квадратний метр усім охочим!
«Інтергал-Буд» вітає з прийдешніми новорічними святами та дарує усім тим, хто хоче придбати квартиру, 1 квадра...
17/08/2021
Майбутні мешканці ЖК «Причал 8» відсвяткували Медовий Спас
14 серпня на території житлового комплексу «Причал 8» святкували Медовий Спас. Девелопер «Інтергал-Буд» влашту...
05/02/2024
«Укргазбанк» акредитував ЖК "Причал 8" до участі в єОселя
Державний «Укргазбанк» акредитував об'єкти на етапі будівництва від компанії «Інтергал-Буд» до участі у пільго...