Dynamics of construction in August

02/09/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in August.

House 1
Section 1

Installation of elevators and commissioning - 98%
Finishing of common areas and special rooms - 99%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 98%

Section 2
Installation of elevators and commissioning - 98%
Finishing of common areas and special rooms - 99%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 99%

Section 3
Roof installation - 95%.
Installation of facades - 98%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 95%
Finishing of common areas and special rooms - 96%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 99%.
Installation of elevators and commissioning - 92%


Section 4
Roof installation - 95%.
Installation of facades - 97%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 90%
Finishing of common areas and special rooms - 96%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 98%.
Installation of elevators and commissioning - 80%

Section 5
Arrangement of a facade - 50%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 90%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 20%
Finishing of common areas and special rooms - 30%
Installation of elevators and commissioning - 25%

Section 6
Installation of a monolith of the 22nd floor
Masonry walls 22 floors

Section 7
Installation of a monolith of the 20nd floor
Masonry walls 15 floors

Parking
Arrangement of a monolithic framework (1 part) - 100%
Arrangement of a facade (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 100%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 10%

House 2
Section 8
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 27%

Section 9
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 25%

Section 10
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 23%


See the full photo report in the section "Construction progress"

Related news

Watch all
03/08/2022
Динаміка будівництва станом на 1 серпня 2022 року
Наразі тривають роботи в будинку №1.  В секціях №1 та №2 ведуться роботи зі встановлення пожежної сигналізаці...
02/05/2024
ГРАФІК РОБОТИ ВІДДІЛІВ ПРОДАЖІВ КОМПАНІЇ НА ВЕЛИКОДНІ СВЯТА
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи відділів пр...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
05/08/2021
Sales schedule is August 6, 2021
Dear buyers! On the occasion of celebrating the Builder's Day, the working schedule of sales departments was ...
06/05/2021
Інформація щодо роботи вебкамери
Друзі!  Через високу динаміку будівництва житлового комплексу «Причал 8» виникла необхідність перенесення веб...
25/11/2020
«Intergal-Bud» and «Ukrgasbank» have improved mortgage conditions
We are pleased to announce that «Intergal-Bud», in partnership with JSB «Ukrgasbank», has offered its clients ...
07/06/2022
Центральний відділ продажів компанії «Інтергал-Буд» відновлює свою роботу
Раді повідомити, що центральний відділ продажів «Інтергал-Буд», який розташований у бізнес-центрі М8 за адресо...
20/08/2024
Зрілість та досвід: компанія «Інтергал-Буд» відзначає 21-річчя
Найбільший приватний забудовник України, компанія «Інтергал-Буд», святкує 21 рік з початку роботи на вітчизнян...
24/07/2024
ОБМЕЖЕННЯ ЕЛЕКТРОПОСТАЧАННЯ НЕ ВПЛИВАЄ НА ТЕМПИ БУДІВНИЦТВА ПРОЄКТІВ «ІНТЕРГАЛ-БУД»
З метою забезпечення безперервної роботи бригад на будмайданчиках компанія «Інтергал-Буд» закупила потужні ген...