Dynamics of construction in August

02/09/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in August.

House 1
Section 1

Installation of elevators and commissioning - 98%
Finishing of common areas and special rooms - 99%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 98%

Section 2
Installation of elevators and commissioning - 98%
Finishing of common areas and special rooms - 99%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 99%

Section 3
Roof installation - 95%.
Installation of facades - 98%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 95%
Finishing of common areas and special rooms - 96%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 99%.
Installation of elevators and commissioning - 92%


Section 4
Roof installation - 95%.
Installation of facades - 97%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 90%
Finishing of common areas and special rooms - 96%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 98%.
Installation of elevators and commissioning - 80%

Section 5
Arrangement of a facade - 50%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 90%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 20%
Finishing of common areas and special rooms - 30%
Installation of elevators and commissioning - 25%

Section 6
Installation of a monolith of the 22nd floor
Masonry walls 22 floors

Section 7
Installation of a monolith of the 20nd floor
Masonry walls 15 floors

Parking
Arrangement of a monolithic framework (1 part) - 100%
Arrangement of a facade (1 part) - 93%
Arrangement of a monolithic framework (2 part) - 100%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 10%

House 2
Section 8
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 27%

Section 9
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 25%

Section 10
Arrangement of a waterproofing, warming of a cellar part of the building - 90%
Monolithic frame device above zero - 23%


See the full photo report in the section "Construction progress"

Related news

Watch all
15/04/2025
Графік роботи відділів продажу на Великдень
Друзі, щиро вітаємо вас з прийдешнім Великоднем! 🐣 Бажаємо тепла, миру та радості у ваших домівках. Звертаєм...
29/11/2023
«СКАЙ БАНК» акредитував об'єкти на первинці від «Інтергал-Буд» до участі в єОселя
Банк-партнер державної програми єОселя, «СКАЙ БАНК», акредитував об'єкти на етапі будівництва від компанії «Ін...
12/02/2024
Динаміка будівництва станом на 09.02.2024 року.
Шановні інвестори! До вашої уваги динаміка будівництва станом на 09.02.2024 року. Будинок №2 Секція 8 Влашт...
13/04/2023
Графік роботи відділу продажів
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи в наступні ...
31/10/2022
ЖК «Причал 8» доєднується до програми «єОселя»
Компанія «Інтергал-Буд» вітає державну ініціативу, яка покликана зробити купівлю житлової нерухомості в іпотек...
31/05/2021
Dynamics of construction in May
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
28/05/2020
Construction Dynamics for May 2020
Dear customers! Your apartments with incredible views of the left bank of the Dnieper do not stop being built!...
10/05/2022
Контактні номери на період військового стану
«Інтергал-Буд» пишається українцями, бо в такий важкий час, ми всі тримаємося міцно.  Ми зібрали список важли...
14/10/2024
Динаміка будівництва на 02.10.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 02.10.2024 року. Будинок №2 Секція 8 Влашт...