Dynamics of construction in February

03/03/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in February.

House 1
Section 1

Installation of facades - 97%
Roof installation - 99%.
Installation of elevators and commissioning - 58%
Finishing of common areas and special rooms - 72%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 60%

Section 2
Roof installation - 99%.
Installation of facades - 98%
Installation of elevators and commissioning - 60%
Finishing of common areas and special rooms - 70%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 58%

Section 3
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Roof installation - 38%.
Installation of facades - 22%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 4%
Finishing of common areas and special rooms - 3%

Section 4
Installation of walls and partitions of the 22nd floor - 99%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 89%.
Roof installation - 3%.

Section 5
Installation of a monolith of the 15th floor
Masonry walls 9 floors

Section 6
Installation of a monolith of the 15nd floor
Masonry walls 6 floors

Section 7
Installation of a monolith of the 10nd floor
Masonry walls 7 floors

Parking
Installation of the foundation slab of the parking pit (1 part) - 99%
Arrangement of a monolithic framework (1 part) - 58%
Installation of the foundation slab of the parking pit (part 2) - 56%
Arrangement of a monolithic framework (2 part) - 27%

House 2
The construction of the pile field continues.

See the full photo report in the section "Construction progress"

Related news

Watch all
04/11/2020
Residential complex PRYCHAL 8 presented to buyers a showroom of apartments with designer renovations
On November 1, on the territory of the residential complex PRYCHAL 8 (Kyiv, Kanalnaya st., 8), a showroom of a...
14/05/2024
Динаміка будівництва на 14.05.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 14.05.2024 року. Будинок №2 Секція 8 Влашт...
25/12/2022
Акційний курс при достроковому погашенні розтермінування
Компанія «Інтергал-Буд» йде на зустріч своїм клієнтам та пропонує вигідні умови дострокового погашення заборго...
18/12/2019
Prychal 8. Construction of 1 and 2 sections of the house №1 is completed
Twenty floors in less than a year. "Intergal-Bud" has completed construction of 1.2 sections of the seven-sect...
04/01/2021
Dynamics of construction in December
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
30/12/2021
Динамика строительства за декабрь 2021
Дом 1 В секции 1, 2, 3, 4 На 98% завершено устройство системы внутреннего водоснабжения и канализации, отопл...
15/07/2024
«ІНТЕРГАЛ-БУД» ОБЛАШТУЄ УКРИТТЯ У КОЖНОМУ ЖИТЛОВОМУ БУДИНКУ
Компанія «Інтергал-Буд» реалізує плани щодо облаштування безпечних приміщень для мешканців своїх будинків, в я...
08/04/2024
Динаміка будівництва березень 2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 09.04.2024 року. Будинок №2 Секція 8 Основ...
02/11/2021
Dynamics of construction in October 2021
Dear customers! For your attention the dynamics of construction of the residential complex "Prychal-8" for Oct...