Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!
We bring to your attention the dynamics of construction in July.
House 1
Section 1
Installation of elevators and commissioning - 99%
Finishing of common areas and special rooms - 99%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 89%
Section 2
Installation of elevators and commissioning - 98%
Finishing of common areas and special rooms - 98%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 98%
Section 3
Roof installation - 90%.
Installation of facades - 97%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 91%
Finishing of common areas and special rooms - 82%
Installation of metal-plastic structures, entrance doors to the apartment and doors - 98%.
Installation of elevators and commissioning - 80%
Section 4
Roof installation - 90%.
Installation of facades - 90%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 86%
Finishing of common areas and special rooms - 80%
Installation of metal-plastic structures, entrance doors to the apartment and doors - 96%.
Installation of elevators and commissioning - 70%
Section 5
Installation of a roof
Arrangement of a facade - 18%
Installation of metal-plastic structures, entrance doors to the apartment and doors - 71%.
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 8%
Finishing of common areas and special rooms - 9%
Section 6
Installation of a monolith of the 20nd floor
Masonry walls 16 floors
Section 7
Installation of a monolith of the 19nd floor
Masonry walls 13 floors
Parking
Arrangement of a monolithic framework (1 part) - 99%
Arrangement of a facade (1 part) - 70%
Arrangement of a monolithic framework (2 part) - 87%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 6%
House 2
Section 8
Arrangement of a waterproofing, warming of a cellar part of the building - 80%
Monolithic frame device above zero - 15%
Section 9
Arrangement of a waterproofing, warming of a cellar part of the building - 50%
Monolithic frame device above zero - 13%
Section 10
Arrangement of a waterproofing, warming of a cellar part of the building - 40%
Monolithic frame device above zero - 12%
See the full photo report in the section "Construction progress"