Dynamics of construction in December

04/01/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in December.

Section 1
Installation of facades - 96%
Roof installation - 98%.
Installation of elevators and commissioning - 54%
Finishing of common areas and special rooms - 68%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 56%

Section 2
Roof installation - 98%.
Installation of facades - 97%
Installation of elevators and commissioning - 56%
Finishing of common areas and special rooms - 67%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 54%

Section 3
Installation of walls and partitions of the 24th floor - 99%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Roof installation - 36%.
Installation of facades - 17%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 2%
Finishing of common areas and special rooms - 1%

Section 4
Installation of walls and partitions of the 22nd floor - 99%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 86%.
Roof installation - 2%.

Section 5
Installation of a monolith of the 12th floor
Masonry walls 6 floors

Section 6
Installation of a monolith of the 12nd floor
Masonry walls 5 floors

Section 7
Installation of a monolith of the 7nd floor
Masonry walls 5 floors

Parking
Installation of the foundation slab of the parking pit (1 part) - 99%
Arrangement of a monolithic framework (1 part) - 47%
Installation of the foundation slab of the parking pit (part 2) - 56%
Arrangement of a monolithic framework (2 part) - 18%

Embankment
Сonstruction of the embankment has begun

See the full photo report in the section "Construction progress"

Related news

Watch all
28/05/2020
Construction Dynamics for May 2020
Dear customers! Your apartments with incredible views of the left bank of the Dnieper do not stop being built!...
23/12/2024
Графік роботи відділів продажу на різдвяно-новорічні свята
Шановні клієнти, Раді повідомити графік роботи наших відділів продажу під час свят: 25 та 31 грудня, 1 та ...
13/04/2023
Графік роботи відділу продажів
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи в наступні ...
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
31/03/2020
We invite you to a video excursion in the territory of Prychal-8
Head of Sales Tatiana Cherednyk will show and tell you everything you wanted to know about the complex with "l...
15/01/2024
Динаміка будівництва станом на 15.01.2024 року
Шановні інвестори! До вашої уваги динаміка будівництва станом на 15.01.2024 року. Будинок №2     Секція 8 ...
20/08/2024
Зрілість та досвід: компанія «Інтергал-Буд» відзначає 21-річчя
Найбільший приватний забудовник України, компанія «Інтергал-Буд», святкує 21 рік з початку роботи на вітчизнян...
15/04/2025
Графік роботи відділів продажу на Великдень
Друзі, щиро вітаємо вас з прийдешнім Великоднем! 🐣 Бажаємо тепла, миру та радості у ваших домівках. Звертаєм...
01/09/2020
Dynamics of construction in August
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...