Dynamics of construction in December

04/01/2021

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in December.

Section 1
Installation of facades - 96%
Roof installation - 98%.
Installation of elevators and commissioning - 54%
Finishing of common areas and special rooms - 68%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 56%

Section 2
Roof installation - 98%.
Installation of facades - 97%
Installation of elevators and commissioning - 56%
Finishing of common areas and special rooms - 67%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 54%

Section 3
Installation of walls and partitions of the 24th floor - 99%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 95%.
Roof installation - 36%.
Installation of facades - 17%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 2%
Finishing of common areas and special rooms - 1%

Section 4
Installation of walls and partitions of the 22nd floor - 99%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 86%.
Roof installation - 2%.

Section 5
Installation of a monolith of the 12th floor
Masonry walls 6 floors

Section 6
Installation of a monolith of the 12nd floor
Masonry walls 5 floors

Section 7
Installation of a monolith of the 7nd floor
Masonry walls 5 floors

Parking
Installation of the foundation slab of the parking pit (1 part) - 99%
Arrangement of a monolithic framework (1 part) - 47%
Installation of the foundation slab of the parking pit (part 2) - 56%
Arrangement of a monolithic framework (2 part) - 18%

Embankment
Сonstruction of the embankment has begun

See the full photo report in the section "Construction progress"

Related news

Watch all
11/03/2022
Важлива інформація про оплату на виплат
Увага! Важлива інформація. Наразі з технічних причин компанія «Інтергал-Буд» не приймає оплати за об’єкти неру...
18/12/2019
Prychal 8. Construction of 1 and 2 sections of the house №1 is completed
Twenty floors in less than a year. "Intergal-Bud" has completed construction of 1.2 sections of the seven-sect...
05/05/2021
Dynamics of construction in April
Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every mont...
17/08/2021
Майбутні мешканці ЖК «Причал 8» відсвяткували Медовий Спас
14 серпня на території житлового комплексу «Причал 8» святкували Медовий Спас. Девелопер «Інтергал-Буд» влашту...
24/07/2024
ОБМЕЖЕННЯ ЕЛЕКТРОПОСТАЧАННЯ НЕ ВПЛИВАЄ НА ТЕМПИ БУДІВНИЦТВА ПРОЄКТІВ «ІНТЕРГАЛ-БУД»
З метою забезпечення безперервної роботи бригад на будмайданчиках компанія «Інтергал-Буд» закупила потужні ген...
02/12/2021
Динамика строительства за ноябрь 2021
Уважаемые покупатели! Вашему вниманию динамика строительства ЖК "Причал-8" за ноябрь 2021: Дом 1 В секции 1,...
12/04/2024
Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики
Компанія «Інтергал-Буд» вносить зміни у всі договори купівлі-продажу нерухомості, додавши пункт про усуненн...
25/07/2024
Будинки від «Інтергал-Буд» матимуть автономне електроживлення
З огляду на складну ситуацію в українській енергетиці компанія «Інтергал-Буд» прийняла рішення внести корек...
03/03/2021
«Інтергал-Буд» першим серед девелоперів приєднався до державної програми «Доступна іпотека 7%»
З 1 березня в Україні стартувала державна програма «Доступна іпотека 7%». Компанія «Інтергал-Буд» стала першим...