Dynamics of construction in September

01/10/2020

Dear buyers! Your homes are growing right before your eyes! And we are happy to record the dynamics every month and share information with you!

We bring to your attention the dynamics of construction in September.

Section 1
Installation of facades - 85%
Roof installation - 95%.
Installation of elevators and commissioning - 30%
Finishing of common areas and special rooms -49%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 30%

Section 2
Roof installation - 95%.
Installation of facades - 85%
Installation of elevators and commissioning - 40%
Finishing of common areas and special rooms -49%
Internal water supply and sewerage system, heating, electricity supply, fire protection systems - 30%

Section 3
Installation of walls and partitions of the 24th floor - 98%
Installation of metal-plastic structures, entrance doors to the apartment and  doors - 60%.

Section 4
Installation of walls and partitions of the 22nd floor - 98%

Section 5
Installation of a monolith of the 7th floor

Section 6
Installation of a monolith of the 5nd floor

Section 7
Installation of a monolith of the 2nd floor

See the full photo report in the section "Construction progress"

Related news

Watch all
21/12/2022
Графік роботи на свята
Шановні клієнти, зверніть, будь ласка, увагу, що відділ продажів ЖК "Причал 8" та відділ супроводу договорів к...
18/12/2019
Prychal 8. Construction of 1 and 2 sections of the house №1 is completed
Twenty floors in less than a year. "Intergal-Bud" has completed construction of 1.2 sections of the seven-sect...
12/04/2021
Візьміть участь у конкурсі «Сад на балконі» від «Інтергал-Буд»!
Закохані у ландшафтний дизайн та навіть брак території вас не зупинив, і ви змогли створити зелену оазу на вла...
02/11/2021
Working hours of the sales department during the period of epidemiological restrictions
Dear customer! Please note that during the period of tightening the restrictions to prevent the spread of COV...
18/07/2024
Динаміка будівництва на 15.07.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 15.07.2024 року. Будинок №2 Секція 8 Влашт...
02/12/2021
Динамика строительства за ноябрь 2021
Уважаемые покупатели! Вашему вниманию динамика строительства ЖК "Причал-8" за ноябрь 2021: Дом 1 В секции 1,...
11/06/2024
Динаміка будівництва на 11.06.2024
Шановні інвестори! До вашої уваги динаміка будівництва станом на 11.06.2024 року. Будинок №2 Секція 8 Влашт...
10/04/2020
Nextbike station is installed on "Prychal-8"
Being mobile is POSSIBLE even during the quarantine. Bike. With its help you can not only easily get to work,...
02/05/2024
ГРАФІК РОБОТИ ВІДДІЛІВ ПРОДАЖІВ КОМПАНІЇ НА ВЕЛИКОДНІ СВЯТА
Щиро вітаємо вас з прийдешнім святом Великодня та просимо звернути увагу на зміни у графіку роботи відділів пр...